Plan the sequence
Crew coordination and crane scheduling helped organize the staged elevator erection.
Moose Jaw area / Supporting experience
Crew coordination and installation work on a grain-cleaning facility.
Explore 8 photos
The facility installation included three bucket elevators, drag conveyors, a support tower, catwalks and a wraparound staircase. Elevator sections and head assemblies were staged for a coordinated multi-crane erection.
Richard carried out installation and crew coordination work with ANB Mechanical.
Crew coordination and crane scheduling helped organize the staged elevator erection.
The elevator heads and connecting catwalk were assembled before lifting into place above the trunking.